— Case studyResidential · 2023
Oceanfront Euro-Wall Installation
New Smyrna Beach, FL·Euro-Wall
— Brief
What we did, why we did it.
A direct-oceanfront Euro-Wall install staged from the beach side. Crane-lifted the great-room panels over the dune line and set them on a single continuous threshold.
— Heaviest panel780 lb
— Lift methodCrane over dune
— Duration9 weeks
— Scope
The spec, in order.
01Crane-staged delivery over the dune
02Euro-Wall 7700 multi-slide on the great room
03Continuous floor track set flush to the deck
04Marine-grade hardware specified for salt exposure
Euro-Wall
— Begin a project